The Ministry of Energy and Natural Resources of RA
The Ministry of Energy and Natural Resources of RA and “MetsamorEnergoAtom” CJSC with the Armavir Marzepetaran held a public hearing at the Armavir Marzpetaran on August 24 regarding the construction of the Armenia New Nuclear Unit to be constructed on the Armenia Nuclear Power Plant Site near Metsamor Town, Armavir Marz.
During the hearing some details of the project were presented by Areg Galstyan, Deputy Minister of Energy and Natural Resources of RA. He informed to the participants of the meeting, that the New Nuclear Unit of RA will replace the generating capacity of the Nuclear Power Plant Unit 2 of RA that currently supplies approximately 40% of the country’s electrical energy.
The New Nuclear Unit will be equipped with the Russian pressurized water energy reactor of the model AES 92 having gross capacity of 1060 MW, with added safety passive systems. The reactor installation of the model AES-92 has been developed based on the Russian Federation, European Utility Requirements (EUR) and International Atomic Energy Agency codes and standards and has a certificate of conformity to the EUR requirements. The design lifetime of the nuclear energy unit of AES-92 is 60 years.
Areg Galstyan also informed, that the construction of the New Nuclear Unit of RA is expected to begin in 2011 with initial site preparation. It will occupy approximately 74 hectare of land, all of which is contained within the existing Nuclear Power Plant of RA site owned by the Government of Armenia; no additional land allocation is needed.
Deputy Minister stated, that the plant staffing for the new unit is estimated at 900 persons. The Armenia New Nuclear Unit will employ a natural draft cooling tower similar to those that serve the existing plant and likely take cooling water from the Sevjur River and a nearby groundwater collection pond (“Lchak”) approximately 7 km from the site. The Armenia New Nuclear Unit will transmit power over the same transmission lines of 110 kV and 220 kV that currently serve the ANPP Unit 2; a new 400 kV transmission line will connect the New Nuclear Unit site to the substation of the Hrazdan 5 thermal power plant. It is possible that new interconnection overhead lines be constructed as well.
The participants of the meeting mainly were interested in the issues concerning the safety securing of the construction and operation of the new nuclear unit. Areg Galstyan stated, that the nuclear unit will be correspond to the international standards and it will be provided with the all necessary safety systems.
As we know, on October 27, 2009, the RoA National Assembly has adopted the RoA Law on Construction of New Nuclear Unit (Units) in Armenia.
On December 3, 2009 a Resolution No. 1458 has been made on Establishment of a Closed Joint-Stock Company for the purpose of construction of New Nuclear Unit (Units) in Armenia.
In accordance with that Resolution of the Government of Armenia, for the purpose of construction of the New Nuclear Unit (Units) in Armenia the CJSC “MetsamorEnergoAtom” has been established.
September 28, 2010