Analysis of Ecological Risks

New Data on SHPPs: Presentation and Discussion
May 30, 2014 at 12:27 | Analysis of Ecological Risks
On 4 June, at 13:00 p.m., the discussion of the report on “Analysis of Small Hydropower Plants (SHPP) Socio-Environmental Impact” will be held dedicated to SHPPs at “Ani Plaza” hotel, “Ani” Hall. The presenters are...
Dali River in Critical Condition
April 26, 2014 at 11:01 | Analysis of Ecological Risks
The Dali River flows in Syunik Region, it’s one of Vorotan tributaries. Its length is 26 km, the catchment basin is 136 km. Its water is used for...
Ayri River Experiencing Crisis
April 24, 2014 at 16:05 | Analysis of Ecological Risks | Syunik
Under the project, the derivation length of the pipeline is 1920 meters, thus the SHPP will pipe a total of 6204 meters, which makes up ...
Gegharot Water Poisonous: Aragats Residents Need Environmentalists’ Help
April 22, 2014 at 13:28 | Analysis of Ecological Risks
Besides two operating HPPs in Aragats Village, the third one is planned to be constructed. The villagers are in horror: they are ready to protest, but they need environmentalists’ help. The Gegharot river doesn’t have even grogs, but ...
Gizhget River in Crisis
April 11, 2014 at 11:31 | Analysis of Ecological Risks | Syunik
“Arevis-1” SHPP is being constructed on this river, under the project its derivation length will be ...
Goght River in Crisis
April 10, 2014 at 15:48 | Analysis of Ecological Risks | Kotayk
The SHPPs pipe a total river area of 5900 meters, which makes up 36.875% of the river