EVEN IN CASE OF WORLD ECONOMIC CRISIS WE ARE STILL COMPETITIVE

Artur Yernjakyan, “ArmInfo”

Questions of Arminfo to Ashot Boghossian, the Regional Director of US Global Gold Corporation

In general, how was the year of 2008 for GGC activities in Armenia? What kind of achievements were recorded and what is your estimation? By what standards one can estimate the year of 2008, as compared with the previous one: investments, volumes of production and processing, explorations…?

2008 was a successful year for us and a turning point in some aspects of our work. During 2008 in Armenia we mainly focused on fundamental business and practical matters of our activity, such as summarizing of the results of geological exploration implemented during previous years, planning the works for coming years in geology based on these results, etc. 2008 was marked by the discovery of reserves in the result of the previously implemented geological exploration and test mining at Toukhmanuk. This discovery significantly increased both the current and long-term economic value of Toukhmanuk deposit. In fact, we discovered a new Toukhmanuk, which is significantly bigger, and with more reserves than previously was known. By the way, this is our main achievement in 2008, which has become possible due to the efforts of the company’s specialists and their consistent work in the geological area. The relevant reports on new reserves at Toukhmanuk are in the final stage of completion and will be submitted for the approval of Armenia’s relevant bodies in the near future. Our next important achievement is that we updated the processing technologies and secured sustainable production at Toukhmanuk, all of which was also achieved in 2008. Our processing plant at Toukhmanuk was technologically and technically modernized at the year end 2008, it entered the stage of sustainable production. Currently, are processing 100,000t of ore annualy, and our currently production potential is from 15-20kg of gold in concentrate each month. We continue developing our Marjan deposit, following the same stages as we did in Toukhmanuk. Initial stage exploration was completed at Marjan, the initial part of the reserves has been confirmed there, and the re-estimation of the reserves is underway. The results of preliminary geological exploration of Getik deposit have been summarized; this deposit is considered to be a perspective one. The year of 2008 was successful also due to the professional and effective cooperation of government officials and employees, which we appreciate.


The previous year was marked by the global economic crisis, which has resulted in many companies’ shut-down and reduction of jobs, including in the mining field. What do you think: has the crisis affected the implementation of GGC projects in Armenia?

I believe that any company will state that the global economic crisis has affected [its] activities. However, the impact depends on various factors, including the level of preparation each company has. We have all witnessed what’s happened with the companies like us involved in, for example, base metals, or for example, those who pursued an unjustified cost policy. As a result, the volume of their problems is incomparably bigger, specifically, in the situation of financial crisis. That situation, fortunately, is different in our case. Specifically, we took into consideration our real possibilities, historical and practical experience, the weaknesses and strengths of the companies of our size, as well as other factors. For example, our leadership in New York considered the dynamics of metals’ prices and potential risks, and made a decision that our company shall focus on gold production. Now it is obvious how correct decision that was. Second, we have never got involved in projects, where we did not believe in advance we could develop them economically efficiently and bring them into production at a considerably lower prime-cost. Third, in due time, we took care of and were consistent in decreasing costs, avoiding possible losses, establishing financial control at a required level and minimized the cost of our production. Due to our consistent work in this direction, and even under the conditions of the economic crisis, we are competitive. Our production cost is substantially lower from its market price, specifically, we produce gold at about $ 340 an ounce, while its market price is about $ 840 an ounce. Indeed, there are an impact of the crisis, and we can see that, for example, the issue of cash may come up from time to time, however, these are structural problems, which will be resolved if our work with financial institutions is restructured, which is now being done. In any case, we fired no employees, and we do not plan to do that. I believe another impact of the crisis is continuously worsening social pressure at our project communities, which is of a concern to us since we are a socially responsible company. However, we continue being useful to the communities, and we will continue assisting them in withstanding the impact of the crisis.

Can you present the current stage of the Company’s projects in Armenia? As far as I know, Toukhmanuk gold deposit is the hugest project from the point of view of already made investments. At the turn of 2007, a small test production of gold was organized here. How much gold did you manage to mine [produce––Anna] in 2008? And what are the other works implemented at Toukhmanuk?

Our Toukhmanuk project can be considered to be an example of a good story in terms of foreign investments. Big investments were made at Toukhmanuk for the purposes of geological exploration and ore processing, including to make dore alloy at the site. Since the end of 2005 up to date, detailed and extensive geological explorations were implemented, about which there were publications in media, including 20,000m of diamond drilling was implemented. Afterwards, the works of that stage were summarized and a test mining was implemented. As a result of all this, we have obtained an ore reserve, which provides with the opportunity to secure a sustainable mining and production at Toukhmanuk. Most importantly, we secured the opportunity to increase the volume of production at Toukhmanuk significantly. Currently, we process around 100,000t of ore, and we are designing a processing plant with a processing capacity of 1mln tones of ore and more, and, hopefully, it will be possible to construct in two-three years. Investments of about $ 30mln will be required to do that. Our shareholders are supportive, we work with them and also with other financial organizations in this direction and we plan to obtain the necessary financing already during this year. We are developing the exploitation project of Marjan following the same pattern, as we did with Toukhmanuk. Mining at Marjan will start following the start of mining at Toukhmanuk. Second-stage works on geological exploration will be implemented at Getik deposit during the upcoming five years, as a result of which, we hope to confirm the initial reserves of the deposit.

Earlier it was reported that the company planned to implement monthly production of 6kg or 200 ounces of gold at Toukhmanuk in summer of 2008 and to come to the level of profitability for the first time. Have you achieved it?

In 2008, around 60,000t of ore was stockpiled from the newly discovered ore bodies at Toukhmanuk, that ore will be processed through the winter, without interruption, until May, after which a new ore will be delivered from the mine to secure uninterrupted production. Due to the new ore bodies discovered at the deposit during 2008, the gold production capacity makes from 15 to 20kg a month. These numbers are substantially higher than the previously announced ones, and we hope to increase the production level also in 2009, due to the increase of the processing plant’s production capacity, by around 1.5 time.

What can you tell about the project of Marjan gold deposit, ROA Syunik region? Has the re-estimation of reserves been implemented? And when the company is going to start the construction of the processing plant and entire infrastructure required for the deposit’s exploitation?

The works of the first stage of Marjan reserves’ re-estimation are completed, and currently they are in the stage of confirmation. We will work towards mining there this year. If things develop the way they are planned, the development of Marjan will proceed by the same way as the development of Toukhmanuk. Marjan will enter a stable production stage simultaneously with the construction of a new processing plant at Toukhmanuk––in two-three years. Before that, we will implement a test mining and will finish the geological exploration of the third stage, as a result of which we expect a substantial increase in the reserves. The results will provide with the opportunity to clarify the economic potential of the mine, however, one can state already now that Marjan can become another big mine. The local community assists us, we appreciate the support of the government, specifically, in this case the Defense Ministry, since Marjan is located in the border zone.

Towards exploitation of which other promising deposits does the company work in Armenia?

Before we get into any project, we do a lot of work, we consider our experience, real possibilities, real prospects, economic, legal and other issues, which may have a decisive importance on the proejct. For example, we never get involved in projects with an unacceptable level of environmental problems. At Toukhmanuk, for example, we plant trees, and sometimes that surprises environmentalists, since they are used to seeing mining companies cutting trees, not planting them at the mines. We do not get involved in projects with complicated ore or metallurgical problems, since, besides high-cost, it may result into environmental problems. We do not get involved in case we are not confident that we can bring the project into a production level efficiently and at a lower prime-cost than the others. It is important for us to ascertain that we can define in advance the volumes of investments required for the project implementation. It is important for us to make sure before we get involved that we can efficiently use our and our specialists’ abilities. It is also important for us to make sure in advance that we will not anyhow disturb the normal life of local people by implementing the project, as well as it is essential that local community is ready to work with us toward the project implementation. There are such projects, which meet these criteria, they are in a preparatory stage, and we will announce about them, as soon as we start them.

February 12, 2009