May 13, 2011 at 11:58 | Mining | Syunik
The State Territorial Environmental Inspection of Syunik Region is still keeping silence, though it should have long disseminated hot information about the emission of dumps in the region inhabited with people and can drink intoxicated water and to get harvest from the intoxicated soil. The Press Service of Nature Protection Ministry doesn’t answer phone calls. Health Ministry is also keeping silence represented by Sanitary Inspection.
May 13, 2011 at 10:57 | Officials | Gegharkunik
Nature Protection Ministry ordered Geopromining Gold Company to submit documentation for the expert assessment which hasn’t been done so far.
May 13, 2011 at 10:31 | Water | Syunik
On 12 May the Administrative Court held the hearing to try the case brought by “For Ensuring Ecological Safety and Developing Democracy” NGO against Nature Protection Ministry, but “ArmWaterCanal” CJSC filed a motion to adjourn the hearing, as the proceedings against “ArmWaterCanal” CJSC are still in progress at Court of Appeal.
May 13, 2011 at 10:18 | Mining | Syunik
In this regard Ecolur asks Demo Gold Mining Company to clear up the situation so as to avoid incorrect interpretations and hearsay till 20 May.
May 12, 2011 at 17:02 | Cities | Yerevan
Green spaces in Yerevan continue to be under attack despite recent assurances by Mayor Karen Karapetyan. These photos were sent to Hetq by Andranik Melikdjanyan, Director of Melikdjanyan Holding.
May 12, 2011 at 15:50 | Officials
In general these draft packages were considered acceptable as the burning down of the wilted vegetation cause damage both to atmospheric air, flora and fauna and statutory prohibition of this harmful deed will prevent its further application.
May 12, 2011 at 15:36 | Nuclear Energy | Armavir
The safety system of Armenian Nuclear Power Plant [ANPP] allows to absolutely rule out possibility of repeating the Fukushima tragedy, Armenian Energy Minister Armen Movsisyan said in the parliament on 11 May.
May 12, 2011 at 14:57 | Cities | Yerevan
After the question and answer session with the government the “Heritage” Faction Leader Stepan Safaryan made an arrangement with Nature Protection and Urban Development Ministers to visit 106 Nalbandyan
May 12, 2011 at 13:54 | Mining
On May 6 the Environmental Public Alliance has sent an open letter to Armenian President Serzh Sargsyan. The letter says
May 12, 2011 at 13:13 | Mining | Gegharkunik
Environmentalists intend to continue their fight against the construction of a crushing and sorting complex by GeoProMining Company in Sotq mine.
May 12, 2011 at 12:19 | Waste | Lori
Even though the tailings dam along the road leading to the Svinets neighborhood in Akhtakla has been closed for the past two years, the threat of the toxins washing into the Akhtala River and then into the Debed River are real.
May 11, 2011 at 19:10 | Sevan | Gegharkunik
EcoLur proposes not to cut down trees for the public beach, but to demolish illegal construction and to use the territories that already have amenities needed.
May 11, 2011 at 18:42 | Cities | Yerevan
'When I came up to one of the peope and asked why they were cutting trees, they said they had the permission of the municipality for pruning. But they were cutting very uncarefully by cutting both dry and green branches,'
May 11, 2011 at 18:10 | Water | Syunik
On May 12 at 17:00 the Administrative Court to try the lawsuit against Nature Protection Ministry filed 'For Ensuring Ecological Safety and Developing Democracy' NGO.
May 11, 2011 at 16:26 | Mining | Gegharkunik
A number of NGOs have applied to the members of the Lake Sevan Issues Committee by Armenian President, Greens Union Chairman Hakob Sanasaryan and “For Sustainable Human Development” Chairman Karine Danielyan with a request to raise the issue of Geopromining Gold Company’s illegal operation in the drainage basin of Lake Sevan at the committee meeting. The company is constructing a crushing and sorting complex without any permitting documents in Sevan drainage basin thus violating RA Law on “Lake Sevan”, while its Article 10 prohibits any ore processing activity in Sevan basin.
May 11, 2011 at 15:52 | Mining | Lori
Vallex Group Company commented EcoLur article entitled ‘Teghut Forest Ecosystem Recovery Made up More Than 32,000 USD for Three Years’ dated on 03.05.2011. Under the company, the article contains mistakes starting from the title.’
May 11, 2011 at 15:17 | Mining | Syunik
As Ecolur was informed from Syunik, on 11 May at about 13:00 the concentrate started building up which runs through the tailing pipe from Zangezour Copper and Molybdenum Combine to Arstvanik Tailing Dump.
May 11, 2011 at 14:06 | Mining | Ararat
Yesterday a group of young people held an ecological cycling race in the frames of “Towards Clean Ararat” demonstration.