ANPP Second Power Unit Stopped for Planned Preventative Rehabilitation

ANPP Second Power Unit Stopped for Planned Preventative Rehabilitation

www.armeniannpp.am

With the view of implementing outage-2020 covering a large scope of activities to be performed in the framework of the ANPP life extension program the ANPP Unit 2 shutdown is planned for July 1, 2020 at 00:00 and the start-up is planned in 65 days, on 3 September. The following main activities are scheduled to be performed during the outage:

1. reactor intermediate maintenance

2. general overhaul of 2 reactor coolant pumps

3. technical inspection of 6 steam generators

4. installation of a new computer information system

5. survey of drives of emergency shutdown, regulating and shim assemblies

6. routine maintenance of steam turbines №3 and 4

7. general overhaul of turbine generator №3

8. activities on flaw inspection of weld seams of metal of the main circulation pipelines and main stop valves.

July 02, 2020 at 17:15