“Megaenergy” LLC has submitted the new, amended working project of “Khachaghbyur-2” SHHP to “Environmental Expertise” SNCO of Nature Protection Ministry of Armenia. The SHHP will be constructed on the Paghjur tributary of the Agstev River.
Reminder: despite public complaints on 26 March 2013 the Nature Protection Ministry issued a positive opinion to the construction project of “Khachaghbyur-2” SHHP, and the construction was launched. In regard with the new project, Armen Vardanyan, Head of Information and Public Relations Department of Nature Protection Ministry explained in his interview with EcoLur, “The project underwent amendments, while each amendment means that the project will be submitted for new environmental expertise.”
February 10, 2014 at 17:56