241.895 Ha of Agricultural Land Areas in Gegharkounik Region Changed Their Category Because of Construction of Solar Photovoltaic Stations

241.895 Ha of Agricultural Land Areas in Gegharkounik Region Changed Their Category Because of Construction of Solar Photovoltaic Stations

The construction of 55 MW Masrik 1 solar photovoltaic plant is planned to start in May 2022. 130 hectares of land area have been provided for the construction of the station, as Chief Secretary of RA Gegharkunik Regional Municipality Sevak Khlghatyan stated in response N02/2377to EcoLur's inquiry dated on 11.04.2022. "Estimate documents have been prepared on the basis of the architectural-planning task of the construction of " Masrik 1 "station. A construction permit has been issued by the community head. Construction is scheduled to begin in May 2022 and will be completed in 2023," the letter says.

According to Public Services Regulatory Commission, 7 solar power plants generate electricity in Gegharkunik Region. 12 solar stations are under construction.

Built solar photovoltaic stations are as follows:

1. "SOL ENERGY" LLC - "Artanish-1" station - Artanish settlement, 2 hectares

2. "GH ENERGY" LLC - "Artanish-2" station - Artanish settlement, 2 hectares

3. "Radpia" Interactive System” LLC - "Shorzha 1" station - Shoghakat settlement, 2 hectares

4. "SOLAR PHARM" LLC - "Solar Pharm" station - Aghberk settlement, 10 hectares

5. "TUFENKYAN HOSPITALITY" LLC - "Heritage" station - Tsapatagh settlement, 10 ha

6. "GH ENERGY" LLC - "Artanish-4" station - Artanish settlement, 2.8 hectares

7. "SOL ENERGY" LLC - "Artanish-3" station - Artanish settlement, 1.2 hectares

Solar photovoltaic stations under construction

1. "FRV Masrik" CJSC - "Masrik-1" station - Mets Masrik settlement, 130 ha

2. "BARI AREV" LLC "Bari Arev" Station - Astghadzor settlement, 7.61 hectares

3. "PROM SAN" LLC - "Prom Synthesis" station - Astghadzor settlement, 8.19 hectares

4. "A-S ENERGY" LLC - "A-S" station - Astghadzor settlement, 8.0 hectares

5. "SOLAR-5" LLC - "5M" station - Aghberk settlement, 9.22 hectares

6. "MODUL-SAN" - "Mets Masrik" station - Mets Masrik settlement, 10.0 hectares

7. "Das Enteria Zolarkftverk" CJSC "Enteria-Shorzha 1" station - Shoghakat settlement, 2.5 ha

8. "ARTSOLAR" LLC - "Artsolar" station - Shoghakat settlement, 5.465 ha

9. "GREEN ENERGY" LLC - "Green Energy" station - Shoghakat settlement, 9.68 ha

10. "ENERGY DESIGN AND CONSTRUCTION" LLC - "Avazan 1" station-Avazan settlement, 1.6 ha

11. "MAGNAK SOLAR" LLC "Arve-1" station - Shoghakat settlement, 10 hectares

12. "MAGNAK SOLAR" LLC "Arev-2" station - Aghberk settlement, 9.63 ha

"All the lands provided for the construction of the mentioned solar photovoltaic power plants were agricultural lands before the change of the intended purpose in the prescribed manner." In other words, a total of 241,895 hectares of agricultural land has been changed for the development of solar energy in Gegharkunik Region.

EcoLur was also interested in how the problems of using, recycling or storing decommissioned solar panels as waste will be resolved. In this regard, the reply letter says: "The service life of the solar panels is 30-40 years, after which they are subject to repair."