SUMMARIZING INTERIM RESULTS OF ANTICRISIS PROGRAM IN AGARAK COPPER AND MOLYBDENUM COMBINE

the Syunyats Yerkir

 Agarak Copper and Molybdenum Combine summarizes interim results of investment anticrisis program carried out in the frames of the government loan in the amount of 14 million USD…

…In the first half of 2010 GeoProMining Company exceeded the plan for overburden operations and reached the highest results for the last 20 years. The company is supposed to carry out overburden operations up to 2,200,000 cubic meters that will enable to significantly increase site development effectiveness. Copper concentrate production in the first chapter of 2010 increased by 12,29 %, while that of molybdenum – by 2,4% as compared with the same period in 2009.

The output makes up 15,153 tons of copper concentrate and 254 tons of molybdenum.

August 18, 2010