ANPP Joined Energetic System of Armenia

ANPP Joined Energetic System of Armenia

On 23 June, 2022 at 13:00 turbine generator №4, then at 20:56 turbine generator №3 of the Armenian NPP Unit 2 were connected to the national grid of Armenia after a 73-day-long stop.

“According to the schedule of outage-2022 the ANPP Unit 2 start-up was planned to be implemented on 27 June, 2022, however thanks to the effective work of the personnel it was implemented 4 days earlier than the scheduled date.

Currently the ANPP is being operated in normal operating mode, at power of 380 MWT, in compliance with safety and reliability standards,” the press release says.

June 27, 2022 at 18:15