November 10, 2022 at 11:46 | Small HPPs, Energy
RA Public Services Regulatory Committee (PSRC) has initiated the process of revising the electricity tariffs delivered from power generating stations using renewable energy resources
November 10, 2022 at 11:22 | Small HPPs, Energy | Yerevan
RA Environment Ministry issued a positive conclusion to the environmental impact application filed by "Armpower" CJSC for the reconstruction of the new combined steam-gas cycle power unit in Yerevan
November 03, 2022 at 12:35 | Small HPPs, Energy | Yerevan
This year, within framework of "Energy Week" event, Yerevan Municipality organized a two-day educational seminar-event entitled "Aware Generation - Sustainable Future"
October 20, 2022 at 10:52 | Small HPPs, Energy
The appreciation of the dram against the dollar can also have a positive effect on the electricity tariff
October 19, 2022 at 16:38 | Small HPPs, Energy | Lori
The committee will discuss the issues raised in your application with the relevant departments to find a legislative solution
October 19, 2022 at 11:32 | Small HPPs, Energy
"EcoLur" Informational NGO participates in the alternative summit and is included in the list of organizations and activists who made their statements for development banks
October 18, 2022 at 13:59 | Small HPPs, Energy | Gegharkunik
The license will be valid until October 13, 2044. The construction period of the station is set until October 13, 2024
October 14, 2022 at 14:21 | Small HPPs, Energy | Gegharkunik
Cyanobacteria-based biofuel, unlike other energy sources, is one of the most environmentally clean and renewable resources
October 13, 2022 at 10:44 | Small HPPs, Energy
The UN weather agency issued an urgent appeal on Tuesday for governments everywhere to switch to cleaner forms of
October 12, 2022 at 15:53 | Small HPPs, Energy | Gegharkunik
The planned capacity of the solar plant is 3.22 MW
October 10, 2022 at 17:18 | Small HPPs, Energy
"FRV Masrik" CJSC, which implements the construction project of "Masrik-1" solar plant, will receive a water use permit
October 10, 2022 at 12:48 | Small HPPs, Energy | Gegharkunik
"FRV Masrik" CJSC, which implements the construction project of "Masrik-1" solar plant, applied to Department of Water Resources Management of Environment Ministry for household-domestic /economic/ underground water use permit
September 30, 2022 at 13:47 | Small HPPs, Energy | Yerevan
During the event, issues related to the development of a new template for the energy performance of buildings certificate (EPB), adaptation of the legal field of Armenia
September 28, 2022 at 15:42 | Small HPPs, Energy | Lori
EcoLur proposed to consider this precedent, which led to a chain of violations of environmental legislation and by-laws involving two state bodies, the Ministry of Environment and PSRC, affected communities and what threatens the existence of the Dzoraget river ecosystem
September 20, 2022 at 13:44 | Small HPPs, Energy | Lori
"Lorva Amrots" is again trying to get a WP to build a small hydropower plant on the Dzoraget river prohibited by RA government's resolution
September 12, 2022 at 11:44 | Small HPPs, Energy | Gegharkunik
"EcoLur" Information NGO addressed RA Environment Minister Hakob Simidyan proposing to revoke the positive expert assessment conclusion issued for the construction of "Masrik-1" solar plant
September 08, 2022 at 09:34 | Small HPPs, Energy | Gegharkunik
Hazardous waste will be collected and stored in a separate place in the area of the intended activity, from where it will be provided to the licensed organization for further activities
September 07, 2022 at 18:05 | Small HPPs, Energy | Gegharkunik
The construction completion date of "Masrik-1" solar photovoltaic station has been extended by more than a year