Annealing Works Completed in ANPP

Annealing Works Completed in ANPP

The activities on annealing of the ANPP Unit 2 reactor vessel metal were completed on 6 August 2021: this process will enable to restore the initial performance properties of the reactor metal for 80-85%, as we learn from the official website of the ANPP.

Prior to the annealing, reactor vessel inspection has been performed using non-destructive methods (visual and instrumental, eddy-current and ultrasonic testing). The work has been implemented by the INETEC specialists (Croatia) through the use of the relevant automated equipment.   

As scheduled, currently re-inspection activities are being performed to compare the results.

Photo Credit: www.armeniannpp.am

August 09, 2021 at 14:12