Throwing Away Money

Throwing Away Money

A. Lalayan, “Zod Wind” CJSC, the Golos Armenii

Wind-power engineering in Armenia and possibility of substituting ANPP capacities

In the republic the electricity consumption for 2009 (the data for 2010 are in the progress of summing up) made up about 5,6 billion kW/h; and the share of the Armenian nuclear power plant in the common generation made up 45%.  At present, the issue of ceasing the operation of Armenian nuclear power plant unit (400 MW) and substituting it with a new reactor with 1000 MW is extremely topical.

The cost of constructing a new unit on the existing area will come to nearly US -6 billion, out of which around 40% of the funding is expected from Russian and Armenian parties. Taking into consideration the latest developments at Japanese Fukushima NPP and international response to the issue of security and safety of operating NPPs, the cost of constructing a new NPP will increase due to additional recalculations of security systems of the designed NPP (both in the sense of seismic, radiation, fire, as well as physical security such as probable acts of international terrorism).

Taking into account the aforementioned factors, the tariff for electricity generation is obvious to be a new significant burden on consumers.

In terms of seismic  security, Armenian nuclear power plant is rather dangerous as it is located in the zone of high seismicity next to tectonic break-up, on the contrary the other consider the Armenian nuclear power plant completely safe and quakes higher than 9 points are impossible in Armenia. The categoricity of the latter cause some doubts. The fact is that Armenian nuclear power plant is in high seismic zone 40 km from Yerevan, where more than 35% of the country population and its whole government, main hospitals and life-support objects, main infrastructures and international airport are concentrated.

The theoretical potential of wind-power engineering in Armenia make up more than 10,000 MW under various estimations, about 10% of which are economically possible to use through the construction of network wind-power engineering. The substitution only that part of generation ensured by Armenian nuclear power plant may cost US ,2 -2,5 billion.